SAP configuration and requirements
IMG setup
Allow the app to post the goods receipt before performing the transfer order creation:
Logistics Execution > Warehouse Management > Activities > Physical Inventory > Define Default Values
Setting the confirmation control key for inbound delivery and/or not relevant for goods receipt:
Materials Management > Purchasing > Confirmations > Set Up Confirmation Control
Prerequisites
For Receipt Directly Against a Purchase Order:
Purchase order items must have a blank confirmation control key or a confirmation control key not relevant for goods receipt.
The material must have batch or serial number information available, if required.
For Receipt Against Inbound Deliveries:
For packed handling units:
Handling units must be created in the delivery, with their contents assigned before processing.
For unpacked delivery items:
Materials requiring batch, production/expiration dates, or serial numbers must have the relevant information available.
For Inbound Deliveries Requiring Putaway Before Goods Receipt:
Putaway must be fully processed prior to using the app for final goods receipt.
A “receipt all” action can be performed if all items are ready.
For Outbound Deliveries from Stock Transport Orders (STOs):
Items must be available and ready to be processed in a manner similar to purchase orders or unpacked inbound deliveries.
For Scheduling Agreements:
Items must have open schedule line quantities that are past due or currently due.
Processing is similar to purchase order items.